Schedule - Subject to Change

January 2013 Project kicks off; survey and field work begin.
February 28, 2013 First public meeting held to gather initial public feedback.
March 2013 Engineering design begins.
June 4, 2013 Second public meeting held to present alignment alternatives and receive public comments.
January 15, 2014 Third public meeting held to review project progress, present final roadway alignment, and show right-of-way and easements that will need to be acquired.
2014 Right-of-way appraisals, negotiation, and acquisition
Fall 2014 Private utilities begin construction.
End of 2014 Design and right-of-way acquisition is substantially complete; city advertises for construction bids.
Early 2015 Project is bid; contract awarded to K2 Construction.
March 19, 2015 Fourth public meeting held to review construction phasing and final plans.
March 30, 2015 Construction for the segment between West Vine Street and West Adams begins.
January 2016 
October 2016
November 2016 
Northbound lanes are completed and traffic is shifted to new lanes.  
Southbound lanes are completed. 
Project final completion 
TBD (funding dependent) Construction for West Adams to Highway 34 begins.
*Please note: All dates are estimates and are subject to change.