January 2013 |
Project kicks off; survey and field work begin. |
February 28, 2013 |
First public meeting held to gather initial public feedback. |
March 2013 |
Engineering design begins. |
June 4, 2013 |
Second public meeting held to present alignment alternatives and receive public comments. |
January 15, 2014 |
Third public meeting held to review project progress, present final roadway alignment, and show right-of-way and easements that will need to be acquired. |
2014 |
Right-of-way appraisals, negotiation, and acquisition |
Fall 2014 |
Private utilities begin construction. |
End of 2014 |
Design and right-of-way acquisition is substantially complete; city advertises for construction bids. |
Early 2015 |
Project is bid; contract awarded to K2 Construction. |
March 19, 2015 |
Fourth public meeting held to review construction phasing and final plans. |
March 30, 2015 |
Construction for the segment between West Vine Street and West Adams begins. |
January 2016 October 2016 November 2016 |
Northbound lanes are completed and traffic is shifted to new lanes. Southbound lanes are completed. Project final completion |
TBD (funding dependent) |
Construction for West Adams to Highway 34 begins. |
*Please note: All dates are estimates and are subject to change. |